Painting an Occupied Condo Community

By Lemoon's Painting

An occupied community is painted one building at a time, in a sequence agreed with the manager, so each household has a defined window of disruption rather than weeks of it. Residents clear patios and balconies, park away from the work, and keep windows closed while their building is sprayed. At least one route in and out of every building stays open throughout.

Painting a community where people live is a different job from painting an empty building. The walls are the same; the constraint is everything around them. Residents still need to get to work, park, let the dog out, receive deliveries and sleep with the windows shut on the nights they are asked to. A good plan accepts that and works with it, building by building.

Telling residents what is coming is its own subject; we have written about keeping residents informed separately. This article is about the physical side: sequence, timing and access.

Why is the work done one building at a time?

So that each household lives with the work for a defined window rather than for the whole project. A community repaint runs from weeks to months, but any single building is in work for a much shorter stretch. Done this way, a resident can plan around their dates, the crew is concentrated where the masking is up, and the manager always knows exactly which part of the property is affected.

The order is agreed with the manager at the start. Common choices are to begin with the buildings in the worst condition, to work outward from the entrance so the community’s face is finished early, or to follow the sun so that hot walls are reached at cooler times of year.

What does a building’s sequence look like?

Each building goes through the same steps Ebenezer follows on any exterior, in the same order:

  1. Notice and clearing. Residents clear patios and balconies and move cars away from the building’s bays.
  2. Power wash. Dirt, chalk and, near the coast, salt come off. Sprinklers aimed at the building are best turned off the day before by the landscaper, so the walls are not re-wetted.
  3. Drying. A washed wall must be dry through before it is coated. In Imperial Beach and other coastal areas that often means the next day.
  4. Repairs. Stucco cracks are opened, filled and textured; soft wood is replaced; rusting metal is treated.
  5. Masking. Windows, doors, light fixtures, walkways, plants, and anything not being painted are covered.
  6. Paint. Body, then trim, doors and metal.
  7. Unmasking and walk. The building is checked, touched up, and handed back.

Residents feel steps one, two, five and six most. The rest happens around them.

What is the daily working window?

It is shorter than people expect, and it is set by the walls rather than the clock. Along the coast and in the western South Bay, a marine layer often leaves surfaces damp well into the morning, and coating a damp wall traps the moisture under the film. Inland, the problem is the opposite: by mid-afternoon in summer a south or west wall can be too hot for the coating to level. The working day follows the dry, moderate part of the day and moves around each building with the sun.

That is also why work near bedrooms does not start at first light. The early hours usually go to preparation, setting up and masking, which are quieter.

How is access to patios and balconies handled?

Most patios and balconies are part of the building’s exterior and need painting, but they are also part of a resident’s home. The manager’s notice should ask residents to clear them and to leave gates unlocked, or to arrange access on their building’s dates. Nobody’s enclosed patio should be entered without that arrangement.

Anything left against a wall is worked around rather than moved, which means the wall behind it may not be painted. Clearing matters.

How do residents get in and out while the paint is wet?

At least one route to every unit stays open at all times. In multi-story buildings with more than one stairway, the stairs are done one at a time. Doors are painted at a point in the day that leaves them dry enough to close by evening. Wet surfaces are marked and taped off, and walkways are kept clear of hoses and equipment when the crew is not using them.

On a property with residents who use walkers or wheelchairs, the manager can tell Ebenezer in advance which routes matter most, and those are planned first.

What about parking, pets and windows?

Parking. Overspray and dripping from eaves and carport beams does not belong on a car. Residents move their vehicles away from the building’s carports or bays on its scheduled days.

Pets. Indoors during washing and painting, for their sake and the crew’s. Dogs in patios are the most common reason a patio is skipped.

Windows. Closed during the building’s spray days. Windows are masked from outside, but a window opened from inside pulls the masking loose.

Who is the board dealing with?

One person. Ebenezer manages every project personally, so the manager has a single contact for the sequence, the weather calls and any resident concern. Weekends are used when the project requires them, and scope is agreed clearly at the start, so a request from a resident that goes beyond it is raised with the manager rather than quietly added. More on HOA painting and maintenance, or on older stucco communities in Chula Vista.

Planning your community’s repaint

If your board is weighing up a repaint and the question is how residents will live through it, that is exactly the conversation to have at the walk. Ebenezer will look at the buildings, the parking, the stairways and the patios, and propose a sequence that keeps the community working. Ask for a free estimate and bring your manager.

Common questions

Do residents have to be home while their building is painted?

Usually not. The exterior can be painted without anyone inside, provided patios and balconies have been cleared and gates are unlocked or access has been arranged with the manager. Residents should keep windows closed during their building's spray days and keep pets indoors.

Can I still use my front door while my building is being painted?

Yes. Doors are painted at a time of day that leaves them dry enough to close by evening, and at least one stairway and walkway to every unit stays open. Wet paint is marked and taped off, so it is clear which route to use.

What do residents need to move before the painters arrive?

Everything on the patio or balcony that sits near a wall: furniture, plants, grills, bikes and decorations, plus anything hanging from the stucco. Cars should be parked away from the building's carports or bays on its scheduled days. The manager's notice will name the dates.

What happens when it rains or the marine layer does not lift?

The building waits. A wet or damp wall cannot be coated without trapping moisture under the film. The sequence shifts by a day, the manager is told, and residents of the affected building are notified. Ebenezer would rather lose a day than paint a damp wall.