Lemoon's Painting CSLB #1120008

Painting While Your Business Stays Open

By Lemoon's Painting

A business can usually stay open while it is repainted, as long as the work is phased. The building is divided into zones, one entrance always stays clear, noisy or smelly steps are moved to the hours you are closed, and each zone is handed back clean before the next one starts. The plan is agreed in writing before the first drop cloth goes down.

Closing a business to repaint it costs more than the paint ever will. A restaurant loses covers, a shop loses its regulars to the one down the street, a clinic has to reschedule patients. So most owners ask the same first question: can you do this while we stay open?

Usually, yes. But only if the job is planned as a sequence of small, finished pieces rather than one big open mess.

What does it mean to phase a paint job?

Phasing means dividing the property into zones and finishing each one completely before starting the next. A zone might be a single wall of the sales floor, the restrooms, the back office, or one elevation of the building outside. Each zone is masked, prepared, painted, inspected and cleaned, then handed back to you, so the rest of the business keeps working normally.

The trade-off is calendar time. Setting up and breaking down a zone every day takes longer than opening the whole building at once. In exchange, your doors stay open the entire time.

Drawing the zones

The zones come from how your customers move, not from where it is convenient to start painting. Before anything is scheduled, Ebenezer walks the space with you and asks:

  • Which entrance do customers actually use, and is there a second one that can serve while the first is painted?
  • Where are the registers, the waiting area, the fitting rooms, the counter?
  • Which rooms can be closed for a day without anyone noticing, and which cannot be closed for an hour?
  • When are you quietest: a weekday morning, a Monday, a closed Sunday?

From those answers comes a written sequence: this zone on these days, that zone after it. You know before the job starts which part of your business is affected on which day.

Keeping one way in, always

The rule that matters most on an open business is that customers always have a clear, safe path from the street to the counter. That means:

  1. Ladders and drop cloths never block the path that is in use.
  2. The entrance being painted is closed off with a barrier and a sign pointing to the one that is open.
  3. Wet paint is marked, and fresh surfaces at hand height (door frames, handrails, push plates) are scheduled so they can dry overnight rather than during trading hours.
  4. Nothing is left on a walkway at the end of the day.

Outside, the same thinking applies to the sidewalk and parking. On a strip center in Chula Vista or a corner building on a busy San Diego street, the front elevation is usually the last zone, done in short windows, because it is the one every customer walks past.

Noise, water and smell: move them to closed hours

Not every step of a paint job is equal. Some are quiet and some are not.

Power washing is loud and wet. On an exterior it is the first step and it cannot be skipped, because chalk, dirt and salt film have to come off or the new coating will not bond. But it can be done before you open or after you close, and the wall then needs time to dry before anything is coated, which often means the next day.

Sanding and scraping produce dust. Inside an occupied space, that work is contained to the zone and done when customers are not there.

Odor is the one owners worry about most. Today’s low-odor interior coatings (both Dunn-Edwards and Sherwin-Williams make lines designed for occupied buildings) smell far less than paint did twenty years ago, but freshly applied paint still has some odor while it dries. Customer-facing rooms are best painted in the evening or on a closed day, with ventilation running, so the room has hours to air out before people come back in.

Cure time is different from dry time. A wall can be dry to the touch in an hour and still be soft enough to scuff when a display is pushed back against it. The label on the product gives the range; the schedule respects it.

Protecting what is already there

An open business has stock, fixtures and equipment in the room. Each zone gets its own protection: displays pulled back from the wall, floors covered, merchandise sealed off with plastic, electronics kept away from any spray. Spray or brush is chosen for each surface, and in an occupied space that often means brush and roller near anything that cannot be moved, even when a sprayer would cover the wall in less time.

Who moves heavy fixtures, and where they go, is written into the scope. It sounds like a small thing. On the morning a fifteen-foot shelving unit has to move, it is not.

The end-of-day reset

Every evening the zone in progress is closed down so the business can open normally the next morning:

  • Tools, ladders and materials stored out of sight or removed.
  • Plastic and drop cloths secured so nothing trips anyone.
  • Floors swept and any drips cleaned while they are still fresh.
  • A short walk with you or your manager, so you know what was done and what happens tomorrow.

That walk is also where questions get answered while they are still small. If something turns up during preparation, such as a damaged section of drywall behind a display or a stucco crack hidden by a sign, Ebenezer tells you what it is, what it involves and how it changes the plan before he goes further. Nothing is added quietly.

Weekends and closed days

Some steps belong on a day the business is shut: the restrooms of a busy café, the dining room of a restaurant, the reception area of an office. Ebenezer works weekends when a project needs it, so the most disruptive pieces can land on the days that cost you least.

One person accountable

On a phased job there are a lot of small handovers, and they go wrong when nobody owns them. Ebenezer manages every project personally, from the first walk-through to the last touch-up, so there is one person who knows the plan and one number to call. He holds a California C-33 Painting and Decorating license, number 1120008, issued to Lemoon’s Painting Inc, and if something is not right once a zone is handed back, he comes back and repairs it.

There is more about how commercial painting is planned, and the step-by-step process behind every job. If you run a business in San Diego, Chula Vista or La Mesa and the thought of closing for a repaint has kept you from doing it, ask for a free estimate. Ebenezer will walk your space during business hours, see how your customers move through it, and show you a zone plan that keeps your doors open.

Common questions

Can you paint my shop without closing it?

In most cases, yes. The work is divided into zones so customers always have a clear way in, and the steps that make noise or smell are moved to the hours you are closed. Whether your space allows it depends on its layout, which is why Ebenezer walks it with you first.

Will the paint smell bother my customers?

Modern low-odor interior coatings smell far less than older paints, but there is still some odor while they dry. Rooms customers use are scheduled for evenings or closed days where possible, with ventilation running, so the space has time to air out before you open again.

What happens to my displays and stock?

They are moved away from the wall being painted and covered, one zone at a time, then returned once the zone is finished. What gets moved, and by whom, is agreed before work starts so nobody is surprised on the morning it happens.

How long does a commercial repaint take?

Weeks to months, depending on the size of the property and how much of the work has to be fitted around your opening hours. Phasing adds calendar days, because each zone is finished and handed back before the next one opens up.